Required: Complete the Production Department’s Flexible Budget Performance Report.

Page 441

Required:

Complete the Production Department’s Flexible Budget Performance Report by filling in all the question marks.

PROBLEM 9–20 Activity and Spending Variances LO9–1, LO9–2, LO9–3

You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president has asked that you review the company’s costing system and “do what you can to help us get better control of our manufacturing overhead costs.” You find that the company has never used a flexible budget, and you suggest that preparing such a budget would be an excellent first step in overhead planning and control.

After much effort and analysis, you determined the following cost formulas and gathered the following actual cost data for March:

  Cost Formula Actual Cost
in March
Utilities $20,600 + $0.10 per machine-hour $24,200
Maintenance $40,000 + $1.60 per machine-hour $   78,100
Supplies $0.30 per machine-hour $8,400
Indirect labor $130,000 + $0.70 per machine-hour $149,600
Depreciation $70,000     $ 71,500

During March, the company worked 26,000 machine-hours and produced 15,000 units. The company had originally planned to work 30,000 machine-hours during March.

Required:

Calculate the activity variances for March. (Hint: Refer to Exhibit 9-6.) Explain what these variances mean.

Calculate the spending variances for March. (Hint: Refer to Exhibit 9-7.) Explain what these variances mean.

Solved
Accounting Equation 1 Answer Muhammad shan